Permits
Permit Requirements
Engineering permits, to be issued by the Engineering Division, are required for all construction activities within private property, dedicated public rights-of-way, and easements, including, but not limited to:
 
  • Curbing
  • Drainage lines and structure
  • Engineering activities
  • Excavation
  • Fill
  • Landscaping
  • Light poles
  • Parking areas
  • Pavement markings
  • Road construction
  • Road cuts
  • Sanitary sewer
  • Sidewalks
  • Swales
  • Traffic signs
  • Waterways
  • Water distribution

Permit Application
Blank forms may be obtained from the Engineering Division:
13975 Pembroke Road
Pembroke Pines, FL 33027
Ph: 954-435-6512
Fx: 954-435-6755

Please complete all blanks. Incomplete or unsigned applications cannot be processed.

Permit Processing
A minimum time period of five working days is required for the processing of a permit application.

Permit Fee
The permit fee is 4% of the construction cost, or as specified otherwise in Sec. 6-16 of the City Code of Ordinances.

Lake Excavation Permit Fee
See the permit fee schedule.

Other Fees
The following fees, if applicable, must be paid prior to the process of this permit application:
  • Engineering Plan Review - $1,521.04 lump sum
  • Street Lights - $1,000.00 per pole

Note: Permit fees are subject to Consumer Price Index.

Drawings & Specifications

Seven sets of drawings and specifications, sealed and signed by the design engineer, which have already been reviewed and approved by the City / county/ state, Health and Rehabilitative Services, Department of Environmental Protection, South Florida Water Management District, South Broward Drainage District, and other applicable review agencies. All approvals must be within a maximum period of 12 months preceding the date of issuance of the permit.

Performance Bond
A performance bond in the amount of 110% of the construction cost, is needed to ensure engineering construction as planned. If the bond has already been submitted to the City, then attach a copy of it.

Construction Contract
A copy of the construction contract which shows the breakdown of all quantities and lump sum cost of the project should be attached with the permit application.

License Qualifications
Up-to-date and valid licenses, registrations, certification,s and insurances should be submitted with each application.

Pavement Cuts
This permit does not cover any pavement cuts on any existing roads, swales, or sidewalks in public rights-of-way. A separate permit must be applied for for such activities.

Pre-Construction Meeting
The pre-construction meeting should be scheduled prior to issuance of the construction permit.

Code of Ordinances
All construction to be performed under a permit must conform to the requirements of the City's Code of Ordinances. The City's Code of Ordinances shall supersede the approved plans and specifications.

Definitions
  • BCWM - Broward County Water Management District
  • CBWCD - Central Broward Water Control District
  • DEP - Department of Environmental Protection
  • DNRP - Department of Natural Resource Protection
  • FDOT - Florida Department of Transportation
  • HRS - Health and Rehabilitative Services
  • SBDD - South Broward Drainage District
  • SFWMD - South Florida Water Management District

Effective Date December, 1995